How does Peak Plan calculate utilization?

Available time is the person's weekly capacity minus internal time and absences, prorated by their working days. Assigned time is the hours of all projects in that week, prorated if an assignment starts or ends mid-week. Under 60% counts as underutilized, up to 85% as healthy, up to 100% as full, and above that as overbooked. None of this is stored; it's recalculated every time you open it.